Contract No: HK/2011/07

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Work (Stage 2)

 

Environmental Permit no. EP-364/2009/B,

Further Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/A and FEP-08/364/2009/A

 

Monthly Environmental Monitoring & Audit Report

 

- september 2012 -

 

CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

Certified by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

11 October 2012


Table of contents          

 

EXECUTIVE SUMMARY. 4

1.     Introduction. 9

1.1        Scope of the Report 9

1.2        Structure of the Report 9

2.     Project Background. 11

2.1        Background. 11

2.2        Scope of the Project and Site Description. 11

2.3        Division of the Project Responsibility. 12

2.4        Project Organization and Contact Personnel 13

3.     status of regulatory compliance. 19

3.1        Status of Environmental Licensing and Permitting under the Project 19

4.     Monitoring Requirements. 30

4.1        Noise Monitoring. 30

4.2        Air Monitoring. 32

5.     Monitoring Results. 34

5.1        Noise Monitoring Results. 34

5.2        Real Time Noise Monitoring Results. 37

5.3        Air Monitoring Results. 38

5.4        Waste Monitoring Results. 40

6.     Compliance Audit. 45

6.1        Noise Monitoring. 45

6.2        Real Time Noise Monitoring. 45

6.3        Air Monitoring. 45

6.4        Review of the Reasons for and the Implications of Non-compliance. 46

6.5        Summary of action taken in the event of and follow-up on non-compliance. 46

7.     Cumulative Construction Impact due to the Concurrent Projects. 46

8.     Environmental Site Audit. 48

9.     Complaints, Notification of Summons and Prosecution. 47

10.    Conclusion. 52


lIST OF TABLES

 

Table 2.1        Schedule 2 Designated Projects under this Project

Table 2.2        Details of Individual Contracts under the Project

Table 2.3        Contact Details of Key Personnel

Table 3.1        Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Table 3.2        Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/17

Table 3.3        Summary of submission status under FEP-03/364/2009

Table 3.4        Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Table 3.5        Summary of submission status under FEP-02/364/2009

Table 3.6        Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Table 3.7        Summary of submission status under FEP-01/364/2009

Table 3.8        Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/18

Table 3.9        Summary of submission status under FEP-05/364/2009/A

Table 3.10      Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Table 3.11      Summary of submission status under FEP-06/364/2009/A

Table 3.12      Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/19

Table 3.13      Summary of submission status under FEP-07/364/2009/A

Table 3.14      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2010/06

Table 4.1        Noise Monitoring Stations

Table 4.2        Real Time Noise Monitoring Stations

Table 4.3        Air Monitoring Stations

Table 5.1        Noise Monitoring Stations for Contract no.  HY/2009/17

Table 5.2        Noise Monitoring Stations for Contract no. HY/2009/18

Table 5.3        Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02

Table 5.4        Noise Monitoring Stations for Contract no. HY/2009/15

Table 5.5        Noise Monitoring Stations for Contract no. HY/2009/19

Table 5.6        Real Time Noise Monitoring Stations for Contract no. HY/2009/17

Table 5.7        Real Time Noise Monitoring Stations for Contract no. HY/2009/19

Table 5.8        Air Monitoring Station for Contract no. HY/2009/17

Table 5.9        Air Monitoring Stations for Contract no. HY/2009/18

Table 5.10     Air Monitoring Station for Contract no. HK/2009/01

Table 5.11     Air Monitoring Station for Contract no. HK/2009/02

Table 5.12     Air Monitoring Station for Contract no. HY/2009/15

Table 5.13     Air Monitoring Stations for Contract no. HY/2009/19

Table 5.14      Details of Waste Disposal for Contract no. HY/2009/17

Table 5.15      Details of Waste Disposal for Contract no. HK/2009/01

Table 5.16      Details of Waste Disposal for Contract no. HK/2009/02

Table 5.17      Details of Waste Disposal for Contract no. HY/2009/18

Table 5.18      Details of Waste Disposal for Contract no. HY/2009/15

Table 5.19      Details of Waste Disposal for Contract no. HY/2009/19

Table 5.20      Details of Waste Disposal for Contract no. HK/2010/06

Table 8.1        Summary of Environmental Inspections for Contract no. HY/2009/15

Table 8.2        Summary of Environmental Inspections for Contract no. HY/2009/18

Table 8.3        Summary of Environmental Inspections for Contract no. HY/2009/19

Table 8.4        Summary of Environmental Inspections for Contract no. HK/2009/01

Table 8.5        Summary of Environmental Inspections for Contract no. HK/2009/02

Table 8.6        Summary of Environmental Inspections for Contract no. HK/2010/06

Table 9.1        Cumulative Statistics on Complaints

Table 9.2        Cumulative Statistics on Successful Prosecutions

Table 10.1      Summary of Key Construction Activities of Individual Contract(s) to be commenced in Coming Reporting Month

 


lIST OF FIGUREs

 

Figure 2.1              Project Layout

Figure 2.2              Project Organization Chart

Figure 4.1              Locations of Environmental Monitoring Stations

 

 

lIST OF APPENDIces

 

Appendix 3.1         Environmental Mitigation Implementation Schedule

Appendix 4.1         Action and Limit Level

Appendix 4.2         Copies of Calibration Certificates

Appendix 5.1         Monitoring Schedule for Reporting Month and Coming month

Appendix 5.2         Noise Monitoring Results and Graphical Presentations

Appendix 5.3         Air Quality Monitoring Results and Graphical Presentations

Appendix 5.4         Real-time Noise Monitoring Results and Graphical Presentations

Appendix 6.1         Event Action Plans

Appendix 6.2         Notification of Exceedance

Appendix 9.1         Complaint Log

Appendix 10.1      Construction Programme of Individual Contracts

EXECUTIVE SUMMARY

  1. This is the Environmental Monitoring and Audit (EM&A) Monthly Report ¡V Sep 2012 specific for Environmental Permit no. EP-364/2009/B, Further Environmental Permit nos. FEP-01/364/2009, FEP-02-364/2009, FEP-03-364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A FEP-07/364/2009/A and FEP-08/364/2009/A. The EM&A report is prepared by the Environmental Team (ET) employed under Contract No. HK/2011/07 ¡V Wan Chai Development Phase II and Central Wanchai Bypass ¡V Sampling, Field Measurement and Testing Works (Stage 2). This report presents the environmental monitoring findings and information recorded during the period August to September 2012. The cut-off date of reporting is at 27th of each reporting month.

 

  1. In the reporting month, the principal work activities of individual contracts are included as follows:

 

Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009

 

¡P          ELS works for basement construction for pile cap construction.

 

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A

¡P          Excavation of trial pit

¡P          Transplanting of trees

¡P          Hoarding erection and modification

¡P          Installation of couplers, UU detection, trial trench, pre-drilling

¡P          Excavation

¡P          Diaphragm wall construction

¡P          Sheet Piling

¡P          Drainage works

¡P          Tunnel works

¡P          Top down slab construction

¡P          Trough structure construction and associated drilling and grouting

¡P          Road works

¡P          OHVD installation

 

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

¡P          Pre-drilling works for CWB (Stage 2) was temporary suspended until the pumping station at dome promenade has been demolished and reclaimed.

¡P          Trimming of SCL Diaphragm wall head

¡P          Construction of SCL top slab (Bay 2 & Bay 1)

¡P          Remedial works for SCL Diaphragm Wall

¡P          Installation of dewatering well for SCL protection works

¡P          Backfilling works on exhaust duct structure

¡P          Excavation down to +2mPD from Ch120 to Ch190 (under HKCEC atrium) at north side of new reclaimed area for subsequent pre-bored H piling works

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

¡P          Diaphragm wall construction of panel P110, P106, P108 and C109

¡P          Deep excavation works reaching -20mPD to -23mPD on the eastern and western portion of the site respectively

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

¡P          Diaphragm wall construction works at TS4

¡P          Rock breaking works at TPCWAE

¡P          Removal of temporary reclamation at TS1

¡P          Dismantling of scaffold in tunnel box at TS1

¡P          Preparation works for bored piling at eastern breakwater

¡P          Mined tunnel preparation works at TPCWAE

 

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

¡P          Road works at Watson Road

¡P          Bored piling (Land)

¡P          Ground contamination  assessment

¡P          Pre-drilling works for bored pile and Diaphragm wall

¡P          D-wall Construction (North & South Section)

¡P          Guide wall construction for D-wall / Barette at North side

¡P          Construction works for Box Culvert T

¡P          Marine Piling

¡P          Construct ion of socket-H pile

¡P          Construction works for Culvert U

¡P          Construction of 1500f drainage pipe

¡P          Construction of Pile cap & column (Land)

 

Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A

¡P          Construction of Pre-cast Unit in China

 


Noise Monitoring

  1. Noise monitoring during daytime was conducted at M1a - Harbour Road Sports Center; M2b - Noon-day gun area; M3a - Tung Lo Wan Fire Station; M4b - Victoria Center; M5b - City Garden, M6 - HK Baptist Church Henrietta Secondary School, M7e and M7w ¡V International Finance Centre Eastern and Western End of Podium, and M8 - City Hall on a weekly basis.
  2. No action and 3 limit level exceedance at M6 ¡V HK Baptist Church Henrietta Secondary School was recorded on 4, 20 and 27 September 2012 in this reporting month.
  3. 24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section Whitefield Depot for the pilling works in FEHD Whitfield Depot and RTN2 ¡V Tunnel (North Point Section) and Island Eastern Corridor Link (IECL).  No action or limit level exceedance was recorded in this reporting month.
  4. As confirmed by CWB RSS, the IECL parapet removal operations will commence in October 2012.  Liaison was conducted with HK Baptist Church Henrietta Secondary School and Po Leung Kuk Yu Lee Mo Fan Memorial School regarding the set up of RTN3 real time noise monitoring station.  Po Leung Kuk Yu Lee Mo Fan Memorial School grant permission for set up on 4 Sep 2012 and station set up was performed on 14 Sep 2012.  The baseline monitoring at RTN3 - Po Leung Kuk Yu Lee Mo Fan Memorial School commenced on 21 Sep 2012.
  5. Oil Street Community Liaison Centre was confirmed to be demolished in mid-October by CWB RSS.  This presented a need for relocation of RTN2 ¡V Oil Street Community Liaison Centre.  After liaison with Hong Kong Electric, permission was granted on 21 Sep 2012 for real time noise monitoring set up at City Garden Electric Centre  (RTN2a ¡V Electric Centre), which is a representative of the noise sensitive receiver City Garden.  The tentative schedule for relocation of RTN2 is on 5 Oct 2012.

 

Air Monitoring

  1. Due to extension of site boundary by contractor of HY/2009/19, location of air monitoring station CMA1b ¡V Oil Street Community Liaison Centre has been finely adjusted on 21 April 2012.
  2. Due to lack of electricity supply, the 24-hr TSP monitoring at the following stations were rescheduled

CMA1b: from 6 and 24 September 2012 to 7 and 25 September 2012

CMA3a: from 18 September 2012 to 19 September 2012

CMA4a: from 24 September 2012 to 25 September 2012

CMA5a: from 31 Aug and 24 September 2012 to 1 and 26 September 2012

MA1e: from 31 August 2012 to 1 September 2012

MA1w: from 6 September 2012 to 7 September 2012

 

  1. 1-hour and 24-hour Total Suspended Particulates (TSP) monitoring were conducted at CMA1b - Oil Street Community Liaison Centre; CMA2a - Causeway Bay Community Center; CMA3a - CWB PRE Site Office Area; CMA4a ¡V Society for the Prevention of Cruelty to Animals; CMA5a - Children Garden opposite to Pedestrian Plaza; MA1e and MA1w ¡V International Finance Centre eastern and western wing on every six days basis. No action and limit level exceedance was recorded in the reporting period.

 

Complaints, Notifications of Summons and Successful Prosecutions

  1. There was no environmental complaint received in this reporting month.

 

Site Inspections and Audit

  1. The Environmental Team (ET) conducted weekly site inspections for Contract no. HY/2009/15, HY/2009/17, HY/2009/18, HY/2009/19, HK/2009/01, HK/2009/02 and HK/2010/06 in this reporting period. The Contractors rectified major observations and recommendations made during the audit sessions. No non-conformance was identified during the site inspections.

 

Future Key Issues

  1. In the coming reporting month, the principal work activities of individual contracts are anticipated as follows:

 

Contract no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009

 

¡P          ELS works for basement construction for pile cap construction.

 

Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A

 

¡P          Excavation of trial pit

¡P          Transplanting of trees

¡P          Hoarding erection and modification

¡P          Installation of couplers, UU detection, trial trench, pre-drilling

¡P          Excavation

¡P          Sheet Piling

¡P          Drainage works

¡P          Tunnel works

¡P          Top down slab construction

¡P          Trough structure construction and associated drilling and grouting

¡P          Road works

¡P          OHVD installation

¡P          Pipe-piling works

¡P          Cooling main bridge construction

¡P          Bridge A construction

¡P          Pre-bored H-pile

 

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009

¡P          Installation of pre-bored H-pile in CWB stage 2 (from Ch120 to Ch190) when the modification of piling rig to suit the low headroom area was completed.

¡P          Remedial works for SCL Diaphragm Wall

¡P          Installation of dewatering system and equipment at SCL

¡P          Backfilling works of the Area 3 to the required level

 

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

¡P          Deep excavation and strut installation works below -20mPD to -23mPD on the eastern and western portion

¡P          Diaphragm wall construction for Panel P116, C107, P114, BHP5, BHP3 and BHP7

 

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

¡P          King Post construction works at TS4

¡P          ELS preparation works at TS4

¡P          Rock breaking works at TPCWAE

¡P          Tunnel works at TS1

¡P          Bored piling at eastern breakwater

¡P          Horizontal drilling along west portal of mined tunnel

 

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

¡P          Road works at Watson Road

¡P          Bored piling (Land)

¡P          Pre-drilling works for bored pile and Diaphragm wall

¡P          D-wall Construction (North & South Section)

¡P          Guide wall construction for D-wall / Barette at North side

¡P          Construction works for Box Culvert T

¡P          Marine Piling

¡P          Construct ion of socket-H pile

¡P          Construction works for Culvert U

¡P          Construction of 1500f drainage pipe

¡P          Construction of Pile cap & column (Land)

¡P          Dismantling of marine platform

¡P          Demolition of parapet at IEC Link

 

Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A

¡P          Construction of Pre-cast Unit in China

1          Introduction

1.1               Scope of the Report

1.1.1.        Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-364/2009/B and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A and FEP-08/364/2009/A to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-014/2001).

1.1.2.        This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and ¡§Environmental Monitoring and Audit Requirements¡¨ under Particular Specification Section 27.

1.1.3.        This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/B, Further Environmental Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A and FEP-08/364/2009/A during the period Aug to Sep 2012. The cut-off date of reporting is at 27th of each reporting month.

 

1.2               Structure of the Report

 

Section 1         Introduction ¡V details the scope and structure of the report.

 

Section 2         Project Background ¡V summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3         Status of Regulatory Compliance ¡V summarizes the status of valid Environmental Permits / Licenses during the reporting period.

 

Section 4         Monitoring Requirements ¡V summarizes all monitoring parameters, monitoring methodology and equipment, monitoring locations, monitoring frequency, criteria and respective event and action plan and monitoring programmes.

 

Section 5         Monitoring Results ¡V summarizes the monitoring results obtained in the reporting period.

 

Section 6         Compliance Audit ¡V summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 7         Cumulative Construction Impact due to the Concurrent Projects ¡V summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8         Site Inspection ¡V summarizes the findings of weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.

 

Section 9         Complaints, Notification of summons and Prosecution ¡V summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 10        Conclusion

2          Project Background

2.1               Background

2.1.1.        ¡§Wan Chai Development phase II and Central-Wan Chai Bypass¡¨ and ¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨ (hereafter called ¡§the Project¡¨) are Designated Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO).  The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.        The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.        There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2               Scope of the Project and Site Description

2.2.1.        Design and Construction of Central ¡V Wan Chai Bypass and Island Eastern Corridor Link under the Project involves the construction and operation of a trunk road and its road tunnel more than 800m in length between portals that is shown at Figure 2.1.

2.2.2.        The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:

¡P          A dual three-lane trunk road, approximately 4.5 km in length, and tunnel approximately 3.7 km in length defined from the connection with the existing Rumsey Street Flyover in Central, through to a connection with the existing Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);

¡P          The Central Interchange near the Rumsey Street Flyover to provide road connections to the Central area;

¡P          Tunnel control buildings and ventilation buildings;

¡P          Slip roads to connect the CWB to the local road system in the Wan Chai North and Causeway Bay area;

¡P          Associated road lighting, road signing, traffic control and surveillance system; and

¡P          Other associated works.

 

2.2.3.        The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1    Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

2.3               Division of the Project Responsibility

2.3.1.        Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced.  Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.        The details of individual contracts are summarized in Table2.2.

Table 2.2    Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HY/2009/17

Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works.

DP1

5 October 2010

HY/2009/18

Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange

DP1

21 April 2011

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010 (Completed)

HK/2009/01

Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works

DP1, DP2

25 August 2011

HK/2009/02

Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East(CWB Tunnel)

DP1

26 April 2011

HY/2009/15

Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

DP1

13 July 2011

HY/2009/19

Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

DP1

24 March 2011

HK/2010/06

Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen Wan Line

DP3

22 March 2011

 

2.4               Project Organization and Contact Personnel

2.4.1.        Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.        The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2.  Key personnel and contact particulars are summarized in Table 2.3:

Table 2.3    Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer¡¦s Representative for WDII

Principal Resident Engineer

Mr. Frankie Fan

2587 1778

2587 1877

Engineer¡¦s Representative for CWB

Principal Resident Engineer

Mr. Peter Poon

3922 3388

3912 3010

Lam Woo & CO., LTD.

Contractor under Contract no. HY/2009/17

General Manager

Mr. Thomas Tang

6111 5351

2566 7522

Contractor¡¦s Representative

Mr. Chung Man Shek

2566 4866

Site Agent

Mr. Tong Au

9725 5874

Environmental Officer

Dr. Priscilla Choy

9161 7287

Environmental Supervisor

Mr. Tam Chun Pong

6461 3062

Chun Wo ¡V Leader Joint Venture

Contractor under Contract no. HK/2009/01

Joint Venture Board Representative

Mr. PL Yue

2162 9909

2634 1626

Site Agent

Mr. Paul Yu

9456 9819

Sub Agent

Mr. Terry Wong

9757 9846

Deputy Site Agent

Mr. Andy Yu

9648 4896

Construction Manager

Mr. Wyman Wong

9627 2467

Construction Manager

Mr. Jack Chu

9775 2467

Construction Manager

Mr KK Yuen

9498 1213

Environmental Officer (Compliance Manager)

Mr. Andy Mak

9103 2370

Environmental Supervisor

Ms. Kiwi Chan

6227 8840

Chun Wo ¡V CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Site Agent

Mr. Chan Sing Cho

3658-3002

2827 9996

Quality & Environmental Manager

(Environmental Officer)

Mr. C.P. Ho

3658-3000

Chun Wo - CRGL - MBEC Joint Venture

 

Contractor under Contract no. HY/2009/19

Project Manager

Mr. Rayland Lee

3758 8879

2570 8013

Site Agent

Mr. Cheung Kit Cheung

6909 1555

Environmental Manager /

Environmental Officer

Mr. M.H. Isa

9884 0810

Environmental Engineer

Calvin Leung

9286 9208

Construction Manager (Marine)

William Luk

9610 1101

Construction Manager

(Land)

Patrick Cheung

9643 3012

Construction Manager

(Land)

Eric Fong

6191 9337

Operation Manager (Land)

Yung Kwok Wah

9834 1010

Leighton Contractors (Asia) Limited

Contractor under Contract no. HY/2009/18

Site Agent

Mr. Brian Gillon

2214 7700

2140 6799

Deputy Site Agent

Mr. Desmond Sze

2214 7703

Environmental Officer

Mr. Anfernee Chow

2214 7721

Environmental Engineer Graduate

Phil Mak

2214 7738

Environmental Supervisor

K. P. Lai

6461 4660

Environmental Supervisor

Ray Cheng

2214 7742

Environmental Supervisor

K. W. Lee

6461 4623

 

 

Environmental Supervisor

Ryan Tsui

2214 7705

 

 

 

Environmental Supervisor

Bosco Lee

2214 7711

 

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Director

Chan Wai Hung

2823 7813

2865 5229

Site Manager

Mr. P.J. Fan

3557 6368

2566 2192

Contractor¡¦s Representative

Mr. David Lau

3557 6358

Head of construction

Mr. Roger Cheung

3557 6371

Environmental Officer

Mr. Daniel Sin

3557 6215

Environmental Supervisor

Mr. Kelven Yip

3557 6347

Gammon -Leader JV

Contractor under Contract no. HK/2010/06

Project Manager

Mr. Paul Lui

9095 7922

2529 2880

Site Agent

Mr. Keith Tse

2529 2068

Environmental Officer

Mr. Lee Wai Man

9481 6024

Environmental Supervisor

Mr. Clement Pang

9735 9200

ENVIRON Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3743 0788

3548 6988

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

2.4.3.        In this reporting month, the principal work activities of individual contracts are included as follows:

Contract no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009

 

¡P          ELS works for basement construction for pile cap construction.

 

Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A

 

¡P          Excavation of trial pit

¡P          Transplanting of trees

¡P          Hoarding erection and modification

¡P          Installation of couplers, UU detection, trial trench, pre-drilling

¡P          Excavation

¡P          Diaphragm wall construction

¡P          Sheet Piling

¡P          Drainage works

¡P          Tunnel works

¡P          Top down slab construction

¡P          Trough structure construction and associated drilling and grouting

¡P          Road works

¡P          OHVD installation

 

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009

¡P          Pre-drilling works for CWB (Stage 2) was temporary suspended until the pumping station at dome promenade has been demolished and reclaimed.

¡P          Trimming of SCL Diaphragm wall head

¡P          Construction of SCL top slab (Bay 2 & Bay 1)

¡P          Remedial works for SCL Diaphragm Wall

¡P          Installation of dewatering well for SCL protection works

¡P          Backfilling works on exhaust duct structure

¡P          Excavation down to +2mPD from Ch120 to Ch190 (under HKCEC atrium) at north side of new reclaimed area for subsequent pre-bored H piling works

 

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

¡P          Diaphragm wall construction of panel P110, P106, P108 and C109

¡P          Deep excavation works reaching -20mPD to -23mPD on the eastern and western portion of the site respectively

 

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

¡P          Diaphragm wall construction works at TS4

¡P          Rock breaking works at TPCWAE

¡P          Removal of temporary reclamation at TS1

¡P          Dismantling of scaffold in tunnel box at TS1

¡P          Preparation works for bored piling at eastern breakwater

¡P          Mined tunnel preparation works at TPCWAE

 

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

¡P          Road works at Watson Road

¡P          Bored piling (Land)

¡P          Ground contamination  assessment

¡P          Pre-drilling works for bored pile and Diaphragm wall

¡P          D-wall Construction (North & South Section)

¡P          Guide wall construction for D-wall / Barette at North side

¡P          Construction works for Box Culvert T

¡P          Marine Piling

¡P          Construct ion of socket-H pile

¡P          Construction works for Culvert U

¡P          Construction of 1500f drainage pipe

¡P          Construction of Pile cap & column (Land)

 

Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A

¡P          Construction of Pre-cast Unit in China

 

2.4.4.        In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

Contract no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009

¡P          ELS works for basement construction for pile cap construction.

 

Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A

¡P          Excavation of trial pit

¡P          Transplanting of trees

¡P          Hoarding erection and modification

¡P          Installation of couplers, UU detection, trial trench, pre-drilling

¡P          Excavation

¡P          Sheet Piling

¡P          Drainage works

¡P          Tunnel works

¡P          Top down slab construction

¡P          Trough structure construction and associated drilling and grouting

¡P          Road works

¡P          OHVD installation

¡P          Pipe-piling works

¡P          Cooling main bridge construction

¡P          Bridge A construction

¡P          Pre-bored H-pile

 

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009

¡P          Installation of pre-bored H-pile in CWB stage 2 (from Ch120 to Ch190) when the modification of piling rig to suit the low headroom area was completed.

¡P          Remedial works for SCL Diaphragm Wall

¡P          Installation of dewatering system and equipment at SCL

¡P          Backfilling works of the Area 3 to the required level

 

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

¡P          Deep excavation and strut installation works below -20mPD to -23mPD on the eastern and western portion

¡P          Diaphragm wall construction for Panel P116, C107, P114, BHP5, BHP3 and BHP7

 

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

¡P          King Post construction works at TS4

¡P          ELS preparation works at TS4

¡P          Rock breaking works at TPCWAE

¡P          Tunnel works at TS1

¡P          Bored piling at eastern breakwater

¡P          Horizontal drilling along west portal of mined tunnel

 

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

¡P          Road works at Watson Road

¡P          Bored piling (Land)

¡P          Pre-drilling works for bored pile and Diaphragm wall

¡P          D-wall Construction (North & South Section)

¡P          Guide wall construction for D-wall / Barette at North side

¡P          Construction works for Box Culvert T

¡P          Marine Piling

¡P          Construct ion of socket-H pile

¡P          Construction works for Culvert U

¡P          Construction of 1500f drainage pipe

¡P          Construction of Pile cap & column (Land)

¡P          Dismantling of marine platform

¡P          Demolition of parapet at IEC Link

 

Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A

¡P          Construction of Pre-cast Unit in China

 

3          status of regulatory compliance

3.1               Status of Environmental Licensing and Permitting under the Project

 

3.1.1.        A summary of the current status on licences and/or permits on environmental protection pertinent to the Project is shown in Table 3.1.

Table 3.1    Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Permits and/or Licences

Reference No.

Issued Date

Status

Environmental Permit

EP-356/2009

30 Jul 2009

Valid

Environmental Permit

EP-364/2009

17 Aug 2009

Superseded

Environmental Permit

EP-364/2009/A

4 Aug 2010

Superseded

Environmental Permit

EP-364/2009/B

20 Sep 2012

Valid

Environmental Permit

EP-376/2009

13 Nov 2010

Valid

Further Environmental Permit

FEP-01/356/2009

18 Feb 2010

Valid

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-04/356/2009

15 Nov 2010

Valid

Further Environmental Permit

FEP-05/356/2009

24 Mar 2011

Valid

Further Environmental Permit

FEP-01/364/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-02/364/2009

21 Apr 2010

Valid

Further Environmental Permit

FEP-03/364/2009

12 July 2010

Valid

Further Environmental Permit

FEP-04/364/2009/A

14 Oct 2010

Surrendered

Further Environmental Permit

FEP-05/364/2009/A

15 Nov 2010

Valid

Further Environmental Permit

FEP-06/364/2009/A

22 Nov 2010

Valid

Further Environmental Permit

FEP-07/364/2009/A

25 Feb 2011

Valid

Further Environmental Permit

FEP-08/364/2009/A

15 June 2012

Valid

 

3.1.2.        Due to the multi-contract nature of the Project, the status of permits and/or licences under the individual contract(s) are presented as below:


Contract no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009

3.1.3.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-03/364/2009 for contract no. HY/2009/17 showed in Table 3.2 and Table 3.3.

Table 3.2    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/17

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-03/364/2009

12 Jul 2010

N/A

Valid

Notification of Works Under APCO

319348

13 Jul 2010

N/A

Valid

Discharge Licence

WT00007212-2010

5 Aug 2010

5 Aug 2010 ¡V 31 Aug 2015

Valid

Registration as a Waste Producer

5213-151-L2608-05

13 July 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance

7010400

16 Mar 2010

N/A

Valid

 

Table 3.3    Summary of submission status under FEP-03/364/2009

EP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

18 September 2010

Conditions 2.7 and 2.8

Submission of works schedule and location plan

1 September 2010

Condition 2.9

Noise Management Plan

1 September 2010

 

Contract no. 04/HY/2006 ¡V Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

3.1.4.        The construction works was completed, and the FEP was surrendered by the Contractor on 11 February 2011.

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009

3.1.5.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.4 and Table 3.5


Table 3.4    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

 

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

N/A

Valid

FEP-02/364/2009

21 Apr 2010

N/A

Valid

Notification of Works Under APCO

313088

6 Jan 2010

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0225-12

02 Mar 2012

14 Mar 2011 to 13  Sep 2012

Valid

(Expired on 13 Sep 2012)

 

GW-RS0227-12

02 Mar 2012

16 Mar 2011 to 15  Sep 2012

Valid

(Expired on 13 Sep 2012)

 

GW-RE0174-12

05 Mar 2012

30 Mar 2012 to  29  Sep 2012

Valid

 

GW-RS0312-12

28 Mar 2012

30 Mar 2012 to  29 Sep 2012

Cancelled

 

GW-RS0314-12

29 Mar 2012

30 Mar 2012 to 25 Sep 2012

Cancelled

 

GW-RS0356-12

03 Apr 2012

11 Apr 2012   to 29 Sep 2012

Valid

 

GW-RS0394-12

16 Apr 2012

19 Apr 2012   to 12 Oct 2012

Valid

 

GW-RS0459-12

3 May 2012

7 May 2012 to  6 Nov 2012

Cancelled

 

GW-RS0460-12

10 May 2012

13 May 2012 to 6 Nov 2012

Valid

 

GW-RS0514-12

14 May 2012

27 May 2012 to 26 Nov 2012

Valid

 

GW-RS0545-12

24 May 2012

26 May 2012 to 25 Nov 2012

Valid

 

GW-RS0546-12

25 May 2012

26 May 2012 to 25 Nov 2012

Valid

 

GW-RS0731-12

5 Jul 2012

05 Jul 2012 to 01 Jan 2013

Cancelled

 

GW-RS0760-12

18 Jul 2012

20 Jul 2012 to 19 Jan 2013

Valid

 

GW-RS0771-12

23 Jul 2012

23 Jul 2012 to 31 Aug  2012

Valid

(Expired on 31 Aug 2012)

 

GW-RS0806-12

3 Aug 2012

4 Aug 2012 to 3 Feb 2012

Valid

 

GW-RS0823-12

3 Aug 2012

3 Aug 2012 to 2 Feb 2012

Valid

 

GW-RS0852-12

16 Aug 2012

16 Aug 2012 to 1 Feb 2012

Valid

 

GW-RS0855-12

16 Aug 2012

17 Aug 2012 to  9 Feb 2012

Valid

 

GW-RS0862-12

20 Aug 2012

28 Aug 2012 to 27 Feb 2012

Valid

 

GW-RS0949-12

12 Sep 2012

16 Sep 2012 to 15 Mar 2013

Valid

 

GW-RS0994-12

25 Sep 2012

25 Sep 2012 to 19 Nov 2012

Valid

 

GW-RS1011-12

26 Sep 2012

30 Sep 2012 to 29 Mar 2013

Valid

 

 

GW-RS1017-12

27 Sep 2012

30 Sep 2012 to 24 Mar 2013

Valid

 

GW-RE0793-12

21 Sep 2012

30 Sep 2012 to 29 Mar 2013

Valid

Discharge Licence

WT00006220-2010

18 Mar 2010

31 Mar 2015

Valid

 

WT00009641-2011

24 Jul 2011

31 Jul 2016

Valid

Billing account under Waste Disposal Ordinance

7010069

21 Jan 2010

N/A

Valid

Registration as a Chemical Waste Producer

WPN5213-134-C3585-01

21 Jan 2010

N/A

Valid

 

Table 3.5    Summary of submission status under FEP-02/364/2009

EP Condition

Submission

Date of Submission

Special Conditions, Clause 2.7 & 2.8

Works Schedule and Location Plan

18 May 2011

Special Conditions, Clause 2.6

Environmental Management Organization Chart

18 May 2011

Special Conditions, Clause 2.6

Commencement Date of Works

25 Jun 2011

Special Conditions, Clause 2.9

Noise Management Plan

10 Jun 2011

 

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

3.1.6.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.6 and Table 3.7.

Table 3.6    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

N/A

Valid

FEP-01/364/2009

24 Mar 2010

N/A

Valid

Notification of Works Under APCO

313962

2 Feb 2010

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0233-12

6 Mar 2012

9 Mar 2012 to 8 Sept 2012

Cancelled

 

GW-RS0255-12

14 Mar 2012

17 Mar 2012 to 15 Sept 2012

Valid

(Expired on 15 Sep 2012)

 

GW-RE0283-12

5 Apr 2012

1 May 2012 to

30 Nov 2012

Valid

 

GW-RS0301-12

20 Mar 2012

21 Mar 2012 to 20 Sept 2012

Cancelled

 

GW-RS0303-12

26 Mar 2012

27 Mar 2012 to 27 Sept 2012

Valid

(Expired on 27 Sep 2012)

 

GW-RS0341-12

3 Apr 2012

28 Apr 2012 to 27 Oct 2012

Valid

 

GW-RS0348-12

3 Apr 2012

10 Apr 2012 to 9 Oct 2012

Valid

 

GW-RS0380-12

12 Apr 2012

1 May 2012 to 31 Oct 2012

Valid

 

GW-RS0388-12

13 Apr 2012

1 May 2012 to 31 Oct 2012

Valid

 

GW-RS0418-12

30 Apr 2012

23 May 2012 to 22 Nov 2012

Valid

 

GW-RS0420-12

30 Apr 2012

18 May 2012 to 17 Nov 2012

Cancelled

 

GW-RS0423-12

30 Apr 2012

19 May 2012 to 18 Nov 2012

Cancelled

 

GW-RS0427-12

30 Apr 2012

23 May 2012 to 22 Nov 2012

Valid

 

GW-RS0445-12

30 Apr 2012

1 May 2012 to 25 Sept 2012

Valid

(Expired on 25 Sep 2012)

 

GW-RS0467-12

10 May 2012

14 May 2012 to 10 Nov 2012

Cancelled

 

GW-RS0533-12

21 May 2012

21 May 2012 to 10 Nov 2012

Valid

 

GW-RS0550-12

25 May 2012

7 June 2012 to 6 Dec 2012

Valid

 

GW-RS0611-12

14 June 2012

15 Jun 2012 to 28 Nov 2012

Valid

 

GW-RS0633-12

13 June 2012

16 Jun 2012 to 14 Dec 2012

Valid

 

GW-RS0671-12

25 June 2012

17 Jul 2012 to 16 Jan 2013

Valid

 

GW-RS0730-12

9 July 2012

10 Jul 2012 to 8 Jan 2013

Valid

 

GW-RS0736-12

9 July 2012

9 Jul 2012 to   8 Jan 2013

Valid

 

GW-RS0739-12

9 July 2012

1 Aug 2012 to 31 Jan 2013

Valid

 

GW-RS0814-12

3 Aug 2012

6 Aug 2012 to 5 Dec 2012

Valid

 

GW-RS0850-12

10 Aug 2012

14 Aug 2012 to 13 Feb 2013

Valid

 

GW-RS0870-12

21 Aug 2012

16 Sept 2012 to 31 Dec 2012

Valid

 

GW-RS0996-12

25 Sept 2012

26 Sept 2012 to 25 Mar 2013

Valid

Construction Noise Permit (CNP) for piling equipment

PP-RS0007-12

27 Mar 2012

28 Mar 2012 to 27 Sept 2012

Cancelled

Discharge Licence

WT00006249-2010

22 Mar 2010

31 Mar 2015

Valid

 

WT00006436-2010

15 Apr 2010

30 Apr 2015

Valid

 

WT00006673-2010

14 May 2010

31 Mar 2015

Cancelled

 

WT00006757-2010

28 May 2010

31 May 2015

Valid

 

WT00007129-2010

28 July 2010

31 Jul 2015

Valid

 

WT00008982-2011

26 April 2011

30 April 2016

Valid

 

WT00009691-2011

1 Aug 2011

31 July 2016

Valid

Billing Account under Waste Disposal Ordinance (Land)

7010255

10 Feb 2010

N/A

Valid

Registration as Chemical Waste Producer (Wan Chai)

WPN5213-135-C3593-01

10 Mar 2010

N/A

Valid

Registration as Chemical Waste Producer (TKO 137)

WPN5213-839-C3593-02

22 Sep 2010

N/A

Valid

 


Table 3.7    Summary of submission status under FEP-01/364/2009

EP Condition

Submission

Date of Submission

Special Conditions, Clause 2.7 & 2.8

Works Schedule and Location Plan

14 Jun 2011

Special Conditions, Clause 2.6

Environmental Management Organization Chart

14 Jun 2011

Special Conditions, Clause 2.6

Commencement Date of Works

21 Jun 2011

Special Conditions, Clause 2.9

Noise Management Plan (Revision A)

13 Jan 2012

Condition 2.11

Landscape Plan (Revision B)

21 Feb 2012

Condition 2.9

Noise Management Plan (Rev.A)

13 Jan 2012

 

Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A

 

3.1.7.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-05/364/2009A for contract no. HY/2009/18 are shown in Table 3.8 and Table 3.9.

Table 3.8    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/18

Permit / Licence / Notification / Approval

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-05/364/2009/A

15 Nov 2010

Permit issued

Valid

Notification of Works Under APCO

322293

07 Oct 2010

Notified

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0261-12

09 Mar 2012

10 Mar 2012 ¡V
09 Sep 2012

Cancelled

 

GW-RS0769-12

23 Jul 2012

25 Jul 2012 ¡V
22 Jan 2013

Valid

 

GW-RS0833-12

09 Aug 2012

25 Jul 2012 ¡V
22 Jan 2013

Valid

 

GW-RS0925-12

31 Aug 2012

3 Sep 2012 ¡V
02 Mar 2013

Valid

Discharge Licence

WT00012998-2012

25 May 2012

31 Jan 2016

Valid

 

WT00012967-2012

17 Sep 2012

30 Sep 2017

Valid

Registration as a Waste Producer

WPN: 8335-121-L1048-04

17 Dec 2010

N/A

Registration completed

Billing Account under Waste Disposal Ordinance (Land)

Account No.: 7011587

11 Oct 2010

Account approved

Valid

 

Table 3.9    Summary of submission status under FEP-05/364/2009/A

EP Condition

Submission

Date of Submission

Condition 2.9

Noise Management Plan

01 March 2011

Condition 2.10

Landscape Plan (Rev. 5)

12 March 2012

 

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

3.1.8.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.10 and Table 3.11

Table 3.10  Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-04/356/2009

22 Nov 2010

N/A

Valid

FEP-06/364/2009/A

22 Nov 2010

N/A

Valid

Notification of Works Under APCO

321822

24 Sep 2010

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0330-12

29 Mar 2012

3 Apr 2012 to

21 Sep 2012

Cancelled

 

GW-RS0328-12

30 Mar 2012

1 Apr 2012 to

22 Sep 2012

Valid

(Expired on 22 Sep 2012)

 

GW-RS0249-12

10 Feb 2012

9 Mar 2012 to

31 Aug 2012

Valid

(Expired on 31 Aug 2012)

 

GW-RS0552-12

24 May 2012

25 May 2012 to

20 Oct 2012

Cancelled

 

GW-RS0586-12

4 Jun 2012

5 Jun 2012 to

30 Sep 2012

Valid

 

GW-RS0695-12

24 Jun 2011

25 Jun 2012 to

21 Dec 2012

Valid

 

GW-RS0700-12

26 Jun 2012

26 Jun 2012 to

25 Dec 2012

Valid

 

GW-RS0607-12

12 Jun 2012

13 Jun 2012 to

7 Dec 2012

Valid

 

GW-RS0789-12

27 Jul 2012

1 Aug 2012 to

25 Jan 2013

Valid

 

GW-RS0924-12

31 Aug 2012

01 Sep 2012 to

28 Feb 2013

Valid

 

GW-RS0984-12

21 Sep 2012

23 Sep 2012 to

22 Mar 2013

Valid

Registration as a Chemical Waste Producer

WPN: 5213-147-C1169-35

15 Nov 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance

7011553

30 Sep 2010

27 Sep 2010 to

27 Jan 2016

Valid

Billing Account under Waste Disposal Ordinance (Dumping by Vessel)

7011761

10 Jul 2012

17 Jul 2012  to

16 Oct 2012

Valid

Water Discharge License (Discharge at TS1)

WT00008780-2011

24 Nov 2011

24 Nov 2011 to 31 Mar 2016

Valid

Water Discharge License (Discharge at  Hung Hing Road)

WT00010482-2011

30 Sep 2011

30 Sep 2011 to 30 Sep 2013

Cancelled

Water Discharge License (Discharge at  CHT area)

WT00012941-2012

10 May 2012

10 May 2012 to 31 May 2014

Valid

Water Discharge License (Discharge at  TPCWAE)

WT00011322-2011

15 Dec 2011

15 Dec 2011 to 31 Dec 2013

Valid

Water Discharge License (Discharge at  TS4)

WT00011718-2012

16 Jan 2012

16 Jan 2012 to 31 Jan 2014

Valid

Table 3.11  Summary of submission status under FEP-06/364/2009/A

EP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

11 Mar 2011

Amendment for Management Organization of Main Construction Companies

16 May 2011

Condition 2.7

Works Schedule

15 Mar 2011

Condition 2.8

Location Plan

15 Mar 2011

Condition 2.23

Noise Management Plan

6 May 2011

 

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

3.1.9.        The current status on licences and/or permits on environmental protection pertinent and submission under FEP-07/364/2009/A for contract no. HY/2009/19 are shown in Table 3.12 and Table 3.13.

Table 3.12  Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/19

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-07/364/2009/A

25 Feb 2011

N/A

Valid

Notification of Works Under APCO

326160

24 Jan 2011

N/A

Valid

Registration as a Waste Producer

7012306

10 Feb 2011

N/A

Valid

Registration as Chemical Waste Producer

5213-151-C3654-01

24 Mar 2011

N/A

Valid

Application for Vessel Disposal

7012306

21 July 2011

N/A

Valid

Construction Noise Permit (CNP)

GW-RS0507-12

22-May-12

(Effective 24-May-12)

23-Nov-12

Cancelled

 

GW-RS0589-12

18-Jun-12

17-Dec-12

Valid

 

GW-RS0286-12

23-Mar-12

(Effective 27-Mar-12)

26-Sep-12

Cancelled

 

GW-RS0871-12

27-Aug-12

26-Feb-13

Valid

 

GW-RS0885-12

27-Aug-12

26-Feb-13

Valid

 

GW-RS0953-12

17-Sep-12

(Effective 21-Sep-12)

20-Mar-13

Valid

Water Discharge Licence

WT00010093-2011

31-Aug-11

30-Sep-16

Cancelled

 

WT00010093-2011

17-Aug-12

30-Sep-16

Valid

 

WT00010865-2011

3-Nov-11

30-Nov-16

Valid

 


Table 3.13  Summary of submission status under FEP-07/364/2009/A

EP Condition

Submission

Date of Submission

Condition 2.9

Noise Management Plan

02 Jun 2011

Condition 2.13

Landscape Plan

16 March 2012

Condition 2.9

Noise Management Plan(Rev.2)

28-Oct-11

 

3.1.10.    Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-08/364/2009/A for contract no. HK/2010/06 showed in Table 3.14 and Table 3.15.

Table 3.14  Cumulative Summary of Valid Licences and Permits under Contract no. HK/2010/06

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-08/364/2009/A

15 June 2012

N/A

Valid

Notification of Works Under APCO

326344

18 Jan 2011

N/A

Valid

Construction Noise Permit (CNP)

GW-RS0923-12

31 Aug 2012

15 Oct 2012 ¡V 14 Apr 2013

Valid from 15 Oct 2012

 

No submission has been made under FEP-08/364/2009/A in this reporting month.

4          Monitoring Requirements

4.1               Noise Monitoring

Noise Monitoring Stations

4.1.1.        The noise monitoring stations for the Project are listed and shown in Table 4.1 and Figure 4.1.  Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.1    Noise Monitoring Stations

Station

Description

M1a

Harbour Road Sports Centre

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

*M7e

International Finance Centre (Eastern End of Podium)

M7w

International Finance Centre (Western End of Podium)

*M8

City Hall

* Remark 1: Location ID has been updated from M7 to M8 for City Hall

* Remark 2: M7e has become a reference station starting from 7 Aug 2012

 

Real time Noise Monitoring Stations

4.1.2.        Review of feasibility on the real time noise monitoring stations was conducted in July with IEC. Station, RTN1a, Tung Lo Wan fireboat Station was found not appropriate to be a monitoring station for monitoring the IECL Piling works and Demolition after visited. 

4.1.3.        The noise monitoring stations for the Project are listed and shown in Table 4.2 and Figure 4.1.. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.2    Real Time Noise Monitoring Stations

District

Station

Description

Tin Hau

RTN1

FEHD Hong Kong Transport Section Whitefield Depot

North Point

RTN2

Oil Street Community Liaison Centre

 

Noise Monitoring Parameters, Frequency and Duration

4.1.4.        The construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq (5 minutes) shall be employed for comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

4.1.5.        Noise monitoring shall be carried out at all the designated monitoring stations. The monitoring frequency shall depend on the scale of the construction activities. The following is an initial guide on the regular monitoring frequency for each station on a weekly basis when noise generating activities are underway:

¡P          One set of measurements between 0700 and 1900 hours on normal weekdays.

4.1.6.        Real time noise shall be carried out at the designated monitoring stations. The following is an initial guide on the regular monitoring frequency for each station on a 24 hours daily basis when noise generating activities are underway:

¡P          One set of measurements between 0700 and 1900 hours on normal weekdays.

¡P          One set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.

¡P          One set of measurements between 2300 and 0700 hours on next day on everyday.

4.1.7.        If construction works are extended to include works during the hours of 1900 ¡V 0700 as well as public holidays and Sundays, additional weekly impact monitoring shall be carried out during respective restricted hours periods. Applicable permits under NCO shall be obtained by the Contractor.

Monitoring Equipment

4.1.8.        As referred to in the Technical Memorandum ™ issued under the NCO, sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise measurement the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

4.1.9.        Noise measurements shall not be made in fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.

4.1.10.    The sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency before deployment to the site and during each site visit. Measurements will be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

 


4.2               Air Monitoring

Air Quality Monitoring Stations

4.2.1.        The air monitoring stations for the Project are listed and shown in Table 4.3 and Figure 4.1.. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.3    Air Monitoring Stations

Station ID

Monitoring Location

Description

CMA1b

Oil Street Community Liaison Centre

North Point (Re-commenced on 14 November 2011)

CMA2a

Causeway Bay Community Centre

Causeway Bay

CMA3a

CWB PRE Site Office *

Causeway Bay

CMA4a

Society for the Prevention of Cruelty to Animals

Wan Chai

CMA5a

Children Garden opposite to Pedestrian Plaza

Wan Chai

MA1e

International Finance Centre (Eastern End of Podium)

Central

MA1w

International Finance Centre (western End of Podium)

Central

Remarks: As per the ENPC meeting in March 2011, the monitoring stations CMA3a ¡V Future CWB site office at Wanchai Waterfront Promenade was renamed as remark.

 

Air Monitoring Parameters, Frequency and Duration

4.2.2.        One-hour and 24-hour TSP levels should be measured to indicate the impacts of construction dust on air quality. The 24-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.

4.2.3.        All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and any other local atmospheric factors affecting or affected by site conditions, etc., shall be recorded down in detail.

4.2.4.        For regular impact monitoring, the sampling frequency of at least once in every six-days, shall be strictly observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three times in every six-days should be undertaken when the highest dust impact occurs.


Sampling Procedure and Monitoring Equipment

4.2.5.        High volume samplers (HVSs) in compliance with the following specifications shall be used for carrying out the 1-hour and 24-hour TSP monitoring:

¡P          0.6 ¡V 1.7 m3 per minute adjustable flow range;

¡P          Equipped with a timing / control device with +/- 5 minutes accuracy for 24 hours operation;

¡P          Installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;

¡P          Capable of providing a minimum exposed area of 406 cm2;

¡P          Flow control accuracy: +/- 2.5% deviation over 24-hour sampling period;

¡P          Equipped with a shelter to protect the filter and sampler;

¡P          Incorporated with an electronic mass flow rate controller or other equivalent devices;

¡P          Equipped with a flow recorder for continuous monitoring;

¡P          Provided with a peaked roof inlet;

¡P          Incorporated with a manometer;

¡P          Able to hold and seal the filter paper to the sampler housing at horizontal position;

¡P          Easily changeable filter; and

¡P          Capable of operating continuously for a 24-hour period.

 

4.2.6.        Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognized primary standard and be calibrated annually. The concern parties such as IEC shall properly document the calibration data for future reference. All the data should be converted into standard temperature and pressure condition.

Laboratory Measurement / Analysis

4.2.7.        A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS accredited.

4.2.8.        Filter paper of size 8¡¨ x 10¡¨ shall be labelled before sampling. It shall be a clean filter paper with no pinholes, and shall be conditioned in a humidity-controlled chamber for over 24-hours and be pre-weighed before use for the sampling.

4.2.9.        After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper shall then be returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable standard.

4.2.10.    All the collected samples shall be kept in a good condition for 6 months before disposal.

4.2.11.    Current calibration certificates of equipments are presented in Appendix 4.2.

5.0        Monitoring Results

5.0.1.        The environmental monitoring will be implemented based on the division of works areas of each designated project managed under different contracts with separate FEP applied by individual contractors.  Overall layout showing work areas of various contracts, latest status of work commencement and monitoring stations is shown in Figure 2.1 and Figure 4.1. The monitoring results are presented in according to the Individual Contract(s).

5.0.2.        In the reporting month, the concurrent contracts are as follows:

Ÿ         Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

Ÿ         Contract no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009

Ÿ         Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A

Ÿ         Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009

Ÿ         Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition Centre

Ÿ         Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central - Wan Chai Bypass at Wan Chai East

Ÿ         Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central - Wan Chai Bypass over MTR Tsuen Wan Line

5.0.3.        The environment monitoring schedules for reporting month and coming month are presented in Appendix 5.1.

5.1               Noise Monitoring Results

5.1.1.        Monitoring for report of review baseline noise level was performed from 11 April 2011 to 8 June 2011.  Then the report was submitted on the 20 June 2011, verified by IEC on 18 July 2011 and was approved by ER by January 2012.  The new baseline is used for the noise calculation of this reporting month starting from January 2012.

Contract no. HY/2009/17 ¡VCentral ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009

5.1.2.        The proposed division of noise monitoring stations for Contract no. HY/2009/17 are summarized in Table 5.1 below:


Table 5.1    Noise Monitoring Stations for Contract no.  HY/2009/17

Station

Description

M4b

Victoria Centre

 

5.1.3.        No action or limit level exceedance was recorded during daytime period in the reporting month. Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2. 

Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A

5.1.4.        Noise monitoring for the Central Interchange works under contract no. HY/2009/18 was commenced on 22 April 2011.The proposed division of noise monitoring stations for Contract no. HY/2009/18 are summarized in Table 5.2 below:

Table 5.2    Noise Monitoring Stations for Contract no. HY/2009/18

Station

Description

*M7e

International Finance Centre (Eastern End of Podium)

M7w

International Finance Centre (Western End of Podium)

M8

City Hall

* Remark : M7e has become a reference station starting from 7 Aug 2012

 

5.1.5.        No action or limit level exceedance was recorded during daytime period in the reporting month.

5.1.6.        Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2.

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009 and Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

5.1.7.        The commencement of construction works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011 and HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of noise monitoring stations are summarized in Table 5.3 below.

Table 5.3    Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02

Station

Description

M1a

Harbour Road Sports Centre

 

5.1.8.        No action or limit level exceedance was recorded in the reporting month.  Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2. 

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

5.1.9.        The commencement of construction works for Contract no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. Noise monitoring was commenced on 13 July 2011. The proposed divisions of noise monitoring stations are summarized in Table 5.4 below.

 

Table 5.4    Noise Monitoring Stations for Contract no. HY/2009/15

Station

Description

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

5.1.10.    No action or limit level exceedance was recorded in this reporting month.

5.1.11.    Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2.

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

 

5.1.12.    Noise monitoring for the tunnel works under contract no. HY/2009/19 was commenced on 24 April 2011. The proposed division of noise monitoring stations are summarized in Table 5.5 below.

Table 5.5    Noise Monitoring Stations for Contract no. HY/2009/19

Station

Description

M3a

Tung Lo Wan Fire Station

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

5.1.13.    No action level exceedance was recorded in the reporting month.

5.1.14.    Three limit level exceedances were recorded on 4, 20 and 27 September 2012 at M6 ¡V HK Baptist Church Henrietta Secondary School in the reporting month.

5.1.15.    Major traffic jam and no major work activities were observed during monitoring, the limit level exceedances were considered as non-project related.

5.1.16.    Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2.  Details of the Notification of Exceedance can be referred in Appendix 6.2.

5.2               Real Time Noise Monitoring Results

5.2.1.        As confirmed by CWB RSS, the IECL parapet removal operations will commence in October 2012.  Liaison was conducted with HK Baptist Church Henrietta Secondary School and Po Leung Kuk Yu Lee Mo Fan Memorial School regarding the set up of RTN3 real time noise monitoring station.  Po Leung Kuk Yu Lee Mo Fan Memorial School grant permission for set up on 4 Sep 2012 and station set up was performed on 14 Sep 2012.  The baseline monitoring at RTN3 - Po Leung Kuk Yu Lee Mo Fan Memorial School commenced on 21 Sep 2012.

5.2.2.        Oil Street Community Liaison Centre was confirmed to be demolished in mid-October by CWB RSS.  This presented a need for relocation of RTN2 ¡V Oil Street Community Liaison Centre.  After liaison with Hong Kong Electric, permission was granted on 21 Sep 2012 for real time noise monitoring set up at City Garden Electric Centre (RTN2a ¡V Electric Centre), which is a representative of the noise sensitive receiver City Garden.  The tentative schedule for relocation of RTN2 is on 5 Oct 2012.

5.2.3.        No construction activity was conducted during nighttime period (2300 to 0700) in this reporting month.

Contract no. HY/2009/17 ¡VCentral ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009 and Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

5.2.4.        The proposed division of noise monitoring stations are summarized in Table 5.6 below. Real time noise monitoring for the piling works under contract no. HY/2009/17 was commenced on 5 October 2010

Table 5.6    Real Time Noise Monitoring Stations for Contract no. HY/2009/17

Location ID

District

Description

RTN1

Tin Hau

FEHD Hong Kong Transport Section Whitefield Depot

Real time noise monitoring results and graphical presentation during night time period are for information only.

5.2.5.        No action and limit level exceedance was recorded in the reporting period.  Real time noise monitoring results measured in this reporting period are reviewed and summarized. Details of real time noise monitoring results and graphical presentation can be referred to Appendix 5.4 .

5.2.6.        The proposed division of noise monitoring stations are summarized in Table 5.7 below. Real time noise monitoring for major construction works under contract no. HY/2009/19 was commenced on 24 April 2011.

Table 5.7    Real Time Noise Monitoring Stations for Contract no. HY/2009/19

Location ID

District

Description

RTN1

Tin Hau

FEHD Hong Kong Transport Section Whitefield Depot

RTN2

North Point

Oil Street Community Liaison Center

Real time noise monitoring results and graphical presentation during night time period are for information only.

5.2.7.        No action or limit level exceedance was recorded in this reporting period.

5.2.8.        Real time noise monitoring results measured in this reporting period are reviewed and summarized. Details of real time noise monitoring results and graphical presentation can be referred to Appendix 5.4 .  Details of the Notification of Exceedance can be referred in Appendix 6.2.

5.3               Air Monitoring Results

5.3.1          Due to extension of site boundary by contractor of HY/2009/19, location of air monitoring station CMA1b ¡V Oil Street Community Liaison Centre has been finely adjusted on 21 April 2012.

5.3.2          Due to lack of electricity supply, the 24-hr TSP monitoring at the following stations were rescheduled:

CMA1b: from 6 and 24 September 2012 to 7 and 25 September 2012

CMA3a: from 18 September 2012 to 19 September 2012

CMA4a: from 24 September 2012 to 25 September 2012

CMA5a: from 31 Aug and 24 September 2012 to 1 and 26 September 2012

MA1e: from 31 August 2012 to 1 September 2012

MA1w: from 6 September 2012 to 7 September 2012

 

Contract no. HY/2009/17 ¡VCentral ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009

5.3.3          The proposed division of air monitoring stations are summarized in Table 5.8 below. Air monitoring for the piling works under contract no. HY/2009/17 was commenced on 8 October 2010.

Table 5.8    Air Monitoring Station for Contract no. HY/2009/17

Station

Description

CMA1b

Oil Street Community Liaison Centre

CMA2a

Causeway Bay Community Centre

5.3.4          No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3. 

Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A

5.3.5          Air monitoring for the Central Interchange works under contract no. HY/2009/18 was commenced on 21 April 2011. The proposed division of air monitoring stations are summarized in Table 5.9 below.

Table 5.9    Air Monitoring Stations for Contract no. HY/2009/18

Station

Description

MA1e

International Finance Centre (Eastern End of Podium)

MA1w

International Finance Centre (Western End of Podium)

 

5.3.6          No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3. 

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009

5.3.7          The commencement of construction works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011. Air quality monitoring was commenced on 25 August 2011. The proposed division of air monitoring stations are summarized in Table 5.10 below.

Table 5.10 Air Monitoring Station for Contract no. HK/2009/01

Station

Description

CMA5a

Children Playgrounds opposite to Pedestrian Plaza

5.3.8          No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3. 

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

5.3.9          The commencement of construction works for HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of air monitoring stations are summarized in Table 5.11 below.

Table 5.11 Air Monitoring Station for Contract no. HK/2009/02

Station

Description

CMA4a

Society for the Prevention of Cruelty to Animals

5.3.10      No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3. 


Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

5.3.11      The commencement of construction works for Contract no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. Air quality monitoring was commenced on 14 July 2011. The proposed division of air monitoring stations are summarized in Table 5.12 below.

Table 5.12 Air Monitoring Station for Contract no. HY/2009/15

Station

Description

CMA3a

CWB PRE Site Office

5.3.12      No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3. 

 

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

5.3.13      The proposed division of air monitoring stations are summarized in Table 5.13 below. Air monitoring for the tunnel works under contract no. HY/2009/19 was commenced on 26 April 2011.

Table 5.13 Air Monitoring Stations for Contract no. HY/2009/19

Station

Description

CMA1b

Oil St Community Liaison Centre

CMA2a

Causeway Bay Community Centre

5.3.14      No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3.

5.4       Waste Monitoring Results

Contract no. HY/2009/17 ¡VCentral ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009

5.4.1.        No Inert and non-inert C&D wastes were disposed in the reporting month. Details of the waste flow table are summarized in Table 5.14


Table 5.14  Details of Waste Disposal for Contract no. HY/2009/17

Waste Type

Quantity this month, m3

Cumulative Quantity-to-Date, m3

Disposal / Dumping Grounds

Inert C&D materials disposed

NIL

NIL

N/A

Inert C&D materials recycled

NIL

1354.82

N/A

Non-inert C&D materials disposed

NIL

NIL

N/A

Non-inert C&D materials recycled

NIL

NIL

N/A

Chemical waste disposed

N/A

N/A

N/A

 

Contract nos. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009

5.4.2.        Inert C&D wastes were recycled and non-inert C&D wastes were disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.15.

Table 5.15  Details of Waste Disposal for Contract no. HK/2009/01

Waste Type

Quantity this month,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

NIL

19,347.225

TKO137, TM38

Inert C&D materials recycled

20

3,077.96

N/A

Non-inert C&D materials disposed

74.06

975.46

SENT Landfill

Non-inert C&D materials recycled

NIL

147,583

N/A

Chemical waste disposed

600

7,900

N/A

 

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

5.4.3.        Inert C&D & non-inert C&D wastes were disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.16.


Table 5.16  Details of Waste Disposal for Contract no. HK/2009/02

Waste Type*

Quantity this month,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

26,509

200,807

TKO137, TM 38

Inert C&D materials recycled

NIL

18,161

WCR2

Non-inert C&D materials disposed

23

609

SENT Landfill

Non-inert C&D materials recycled

NIL

NIL

N/A

Chemical waste disposed (kg)

800

5,521

N/A

Remarks Contractor clarified and updated waste flow table for the reporting month of Sep 2012

Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A

 

5.4.4.        Inert C&D and non-inert C&D waste was disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.17.

Table 5.17  Details of Waste Disposal for Contract no. HY/2009/18

Waste Type*

Quantity this month,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

5776

53860

T.K.O. 137, TM 38

Inert C&D materials recycled

5732

24563

N/A

Non-inert C&D materials disposed

112

740

SENT Landfill

Non-inert C&D materials recycled (tonnes)

9.07

70.17

N/A

Chemical waste disposed (kg)

NIL

2,985

N/A

 

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

5.4.5.        Inert & Non-inert C&D wastes were disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.18.


Table 5.18  Details of Waste Disposal for Contract no. HY/2009/15

Waste Type*

Quantity this month, m3

Cumulative-to-Date, m3

Disposal / Dumping Grounds

Inert C&D materials disposed

8,868.8

170,872.2

Tuen Mun Area 38

 

218.9

150,031.1

TKO137 FB

Inert C&D materials recycled

7,145.8

7,561.7

HY/2009/11

ex-PCWA

TS4

TS2

Non-inert C&D materials disposed

40.3

503.5

SENT Landfill

Non-inert C&D materials recycled (kg)

NIL

542,431.5

Xun Xiang Metalware

Skylight Recycle (paper)

Chemical waste disposed (kg)

NIL

11,036

Dunwell Group

 

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

5.4.6.        Inert and Non-inert C&D wastes were disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.19.

Table 5.19  Details of Waste Disposal for Contract no. HY/2009/19

Waste Type*

Quantity this month,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

18,999.07

167,378.31

N/A

Inert C&D materials recycled

NIL

1,801.91

N/A

Non-inert C&D materials disposed

28.85

569.07

SENT Landfill

Non-inert C&D materials recycled

NIL

42.81

N/A

Chemical waste disposed

NIL

4.42

N/A

Remarks: Contractor clarified and updated waste flow table for the reporting period of June to August 2012.

Contract no. HK/2010/06 Wan Chai Development Phase II - Central-Wan Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A

5.4.7.        No inert and Non-inert C&D wastes were disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.20.


Table 5.20  Details of Waste Disposal for Contract no. HK/2010/06

Waste Type*

Quantity this month,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

NIL

NIL

TM38

Inert C&D materials recycled

NIL

NIL

N/A

Non-inert C&D materials disposed

NIL

NIL

N/A

Non-inert C&D materials recycled

NIL

NIL

Recyclers

Chemical waste disposed

NIL

NIL

N/A

 

 

6          Compliance Audit

6.0.1.        The Event Action Plan for construction noise, air qualities are presented in Appendix 6.1.

6.1               Noise Monitoring

 

Contract no. HY/2009/17 ¡VCentral ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009

6.1.1.        No exceedance was recorded in the reporting month.

Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A

6.1.2.        No exceedance was recorded in the reporting month.

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009

6.1.3.        No exceedance was recorded in the reporting month.

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

6.1.4.        No exceedance was recorded in the reporting month.

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

6.1.5.        No exceedance was recorded in the reporting month.

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

6.1.6.        Three limit level exceedances were recorded at M6 ¡V HK Baptist Church Henrietta Secondary School on 4, 20 and 27 September 2012 in the reporting month.  Investigations found that major traffic noise was contributed in the noise monitoring and not related to the Project.

Real Time Noise Monitoring

Contract no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009

6.1.7.        No exceedance was recorded in the reporting month.

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

6.1.8.        No action or limit level exceedance was recorded in this reporting period.

6.2               Air Monitoring

 

Contract no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009

6.2.1.        No exceedance was recorded in the reporting month.

 

Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A

6.2.2.        No exceedance was recorded in the reporting month.

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009

6.2.3.        No exceedance was recorded in the reporting month.

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

6.2.4.        No exceedance was recorded in the reporting month.

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) FEP-06/364/2009/A

6.2.5.        No exceedance was recorded in the reporting month.

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

6.2.1          No exceedance was recorded in the reporting month.

6.3               Review of the Reasons for and the Implications of Non-compliance

6.3.1.        There was no non-compliance from the site audits in the reporting period. The observations and recommendations made in each individual site audit session were presented in Section 8.

6.3.2.        No project-related non-compliance from monitoring was recorded in the reporting month.

6.4               Summary of action taken in the event of and follow-up on non-compliance

6.4.1          There was no particular action taken since no project-related non-compliance was recorded from the site audits and environmental monitoring in the reporting period.


7                     Cumulative Construction Impact due to the Concurrent Projects

7.0.1.        According to Condition 3.4 of the EP-364/2009/B, this section addresses the relevant cumulative construction impact due to the concurrent activities of the current projects including the Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) and Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel).

7.0.2.        According to the Monthly EM&A report (Aug 2012) of Central Reclamation Phase III (CRIII), filling works, road works, building construction works and pipe works were performed in the September 2012 reporting month. The water quality monitoring was completed in October 2011 and no exceedance was recorded for air and noise monitoring.  It can be concluded that cumulative construction impact due to the concurrent activities of the current projects with the Central Reclamation Phase III (CRIII) was insignificant.

7.0.3.        According to the construction programme of Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, the major construction activity under Wan Chai Development Phase II was marine works at HKCEC areas, cross-harbour Watermains, Fresh Watermains, Cooling Watermains and Salt Watermains Installations, tunnel works at Wan Chai East, diaphragm wall construction at TS4; dredging at TS2 and deep excavation at TPCWAE TCBR1W. Advanced piling works at FEHD Whitfield Depot, Central Interchange, and diaphragm wall construction at North Point area. The major environmental impact was water quality impact at Causeway Bay and Wan Chai. Land-based construction activity were Diaphragm wall construction at TS4, deep excavation at TPCWAE TCBR1W, piling works at FEHD Whitfield Depot, Diaphragm wall at Central and North Point and tunnel works at Wan Chai East in the reporting month.

7.0.4.        The major environmental impacts generated from advanced piling works at FEHD Whitfield Depot were undertaken and Diaphragm wall construction at Central and tunnel works at Wan Chai East, IECL and Causeway Bay Typhoon Shelter in the reporting month. No significant air impact was anticipated in the reporting month. Besides, no Project-related exceedance was recorded during the environmental monitoring events in the reporting month.  Thus, it is evaluated that the cumulative construction impact from the concurrent projects including Wan Chai Development Phase II was insignificant.

8          Environmental Site Audit

8.0.1.        During this reporting month, weekly environmental site audits were conducted for Contracts no. HY/2009/15, HY/2009/17, HY/2009/18, HY/2009/19, HK/2009/01, HK/2009/02 and HK/2010/06. No non-conformance was identified during the site audits.

8.0.2.        Five site inspections for Contract no. HY/2009/15 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.1.

Table 8.1    Summary of Environmental Inspections for Contract no. HY/2009/15

Date

Item

Observations

Action taken by Contractor

Outcome

28-Aug-12

120828_01

No stock of silt curtain, impermeable barrier and geotextile was available on site (TS1).

Stock of impermeable barriers and silt curtains were stored on storage facility at North Point.

Completion as observed on 4-Sep-12

28-Aug-12

120828_02

Silt curtains and impermeable barriers were observed to be inadequate at TS1.  Better maintenance should be performed to avoid gaps & holes. (Diaphragm wall, TS1)

Works at TS1 were completed.

Completion as observed on 4-Sep-12

28-Aug-12

120828_03

Mud was observed on the seawall blocks, contractor should clear it to avoid runoff into sea.  Protection should also be provided (Eastern Breakwater, TS1).

Mud was cleared from the seawall blocks.

Completion as observed on 4-Sep-12

28-Aug-12

120828_04

Haul roads should be kept wet (TS4)

Haul roads were sprayed with water.

Completion as observed on 4-Sep-12

18-Sep-12

120918_01

Silty water was observed to be discharging at discharge point.  Contractor immediately stopped discharging, but the contractor is recommended to review the frequency of sludge removal at water treatment plants (TS4)

Sludge was removed.

Completion as observed on 25-Sep-12

25-Sep-12

120925_01

Oil leakage should be cleared up as chemical waste.  Preventive measures should be provided for prevention of oil leakage.  Drip trays should also be provided for oil/chemical drums.

Oil leakage was cleared.

Completion as observed on 3-Oct-12

 

8.0.3.        Five site inspections for Contract no. HY/2009/18 was carried out during this reporting period.  No observations was found in the reporting month.

8.0.4.         Five site inspections for Contract no. HY/2009/19 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.2.

Table 8.2    Summary of Environmental Inspections for Contract no. HY/2009/19

Item

Date

Observations

Action taken by Contractor

Outcome

120830_01

30-Aug-12

The oil stain was observed on the ground which should be removed and disposed as chemical waste (Portion3, D7 and Portion 6, F5)

Oil stain was removed as chemical waste.

Completion as observed on 12-Sep-12

120912_01

12-Sep-12

Oil leakage was observed on the water surface and on platform 9.  The contractor should provide measures to prevent further leakage.

Oil leakage was removed and tarpaulin sheet was provided below the leaking plant.

Completion as observed on 19-Sep-12

120926_01

26-Sep-12

Oil leakage was observed at some plants & vehicles, the contractor is recommended to provide adequate measures to prevent leakage and treat leakage as chemical waste.  Also, the contractor is recommended to provide training to all staff on how to handle chemical waste (Portion VII & Platform FVII)

Oil leakage was removed.

Completion as observed on 3-Oct-12

8.0.5.        Five site inspections for Contract no. HK/2009/01 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.3.

Table 8.3    Summary of Environmental Inspections for Contract no. HK/2009/01

Item

Date

Observations

Action taken by Contractor

Outcome

120829_01

29-Aug-12

The oil stain should be removed and disposed as chemical waste. (VIP area)

The oil stain was removed

Completion as observed on 5-Sep-12

120905_01

5-Sep-12

Drip trays should be provided for oil drums (TST)

The oil drums were removed.

Completion as observed on 12-Sep-12

120912_01

12-Sep-12

The soil from the site area was observed on the public area which should be removed immediately (A4-3)

The exposed soil was removed

Completion as observed on 20-Sep-12

120912_02

12-Sep-12

The construction materials should be moved away from the plants (A1-1)

The construction material was removed.

Completion as observed on 20-Sep-12

120920_02

20-Sep-12

Existing trees to be retained shall be kept free from construction materials (C1 Site office)

The construction material was removed.

Completion as observed on 26-Sep-12

120926_01

26-Sep-12

Drip tray should be provided for oil drums (Water Channel)

The oil drums were removed.

Completion as observed on 3-Oct-12

 

8.0.6.        Five site inspections for Contract no. HK/2009/02 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.4.

Table 8.4    Summary of Environmental Inspections for Contract no. HK/2009/02

Item

Date

Observations

Action taken by Contractor

Outcome

120830_01

30-Aug-12

The valid noise emission label should be displayed on hand-held breaker (SPCA)

The hand-held breaker was removed from the site.

Completion as observed on 6-Sep-12

120830_02

30-Aug-12

The measures should be taken to improve the efficiency of wheel washing facilities (Small Ex-pet garden, Gate 2 in WCR1)

The efficiency of wheel washing facilities has been improved.

Completion as observed on 6-Sep-12

120906_01

6-Sep-12

The stockpile should be covered by tarpaulin sheet (Small Ex-pet garden)

The stockpile was removed,

Completion as observed on 13-Sep-12

120919_01

19-Sep-12

The lubricating oil was observed on ground which should be cleaned and removed as chemical waste (WCR1)

The oil was removed.

Completion as observed on 26-Sep-12

8.0.7.        Five site inspections for Contract no. HY/2009/17 were carried out during this reporting period. No observation was found in the reporting month.

8.0.8.        Four site inspections for Contract no. HK/2010/06 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.5.

Table 8.5     Summary of Environmental Inspections for Contract no. HK/2010/06

Item

Date

Observations

Action taken by Contractor

Outcome

120903_01

3-Sep-12

The U-channel should be connected with oil interceptor (2w)

 

The u-channel was connected with oil interceptor

Completion as observed on 10-Sep-12

 

9          Complaints, Notification of Summons and Prosecution

9.0.1.        No environmental complaint was received in the reporting period.

9.0.2.        The details of cumulative complaint log and updated summary of complaints are presented in Appendix 9.1

9.0.3.        Cumulative statistic on complaints and successful prosecutions are summarized in Table 9.1 and Table 9.2 respectively.

Table 9.1    Cumulative Statistics on Complaints

Reporting Period

No. of Complaints

Sep 12

0

Sep 10 to Aug 12

20

Total

20

 

Table 9.2    Cumulative Statistics on Successful Prosecutions

Environmental Parameters

Cumulative No. Brought Forward

No. of Successful Prosecutions this month (Offence Date)

Cumulative No. Project-to-Date

Air

-

0

0

Noise

-

0

0

Water

-

0

0

Waste

-

0

0

Total

-

0

0

10                 conclusion

10.0.1.    The EM&A programme was carried out in accordance with the EM&A Manual requirements, minor alterations to the programme proposed were made in response to changing circumstances.

10.0.2.    The scheduled construction activities and the recommended mitigation measures for the coming month are listed in Table 10.1. The construction programmes of individual contracts are provided in Appendix 10.1.

Table 10.1     Summary of Key Construction Activities of Individual Contract(s) to be commenced in Coming Reporting Month

Contract No.

Key Construction Works

Recommended Mitigation Measures

HY/2009/15

¡P         King Post construction works at TS4

¡P         ELS preparation works at TS4

¡P         Rock breaking works at TPCWAE

¡P         Tunnel works at TS1

¡P         Bored piling at eastern breakwater

¡P         Horizontal drilling along west portal of mined tunnel

¡P         Watering any dust generating activities

¡P         Checking all drip trays frequently and clear any stagnant water and mud inside it.

¡P         Noise control measures shall be provided during restricted hours.

 

HY/2009/17

¡P         ELS works for basement construction for pile cap construction.

¡P         Noise barrier shall be implemented; and

¡P         Watering any dust generating activities

HY/2009/18

¡P         Excavation of trial pit

¡P         Transplanting of trees

¡P         Hoarding erection and modification

¡P         Installation of couplers, UU detection, trial trench, pre-drilling

¡P         Excavation

¡P         Sheet Piling

¡P         Drainage works

¡P         Tunnel works

¡P         Top down slab construction

¡P         Trough structure construction and associated drilling and grouting

¡P         Road works

¡P         OHVD installation

¡P         Pipe-piling works

¡P         Cooling main bridge construction

¡P         Bridge A construction

¡P         Pre-bored H-pile

¡P         Noise barrier shall be implemented; and

¡P         Noise level shall be controlled by reducing piling rate and no. of plants working in parallel.

¡P          Dust control during dust generating works

¡P          Provide protection works to ensure no runoff out of site area or direct discharge into public drainage system.

¡P          Appropriate plants and measures should be taken to ensure adequate protections are provided for trees being transplanted.

HY2009/19

¡P         Road works at Watson Road

¡P         Bored piling (Land)

¡P         Pre-drilling works for bored pile and Diaphragm wall

¡P         D-wall Construction (North & South Section)

¡P         Guide wall construction for D-wall / Barette at North side

¡P         Construction works for Box Culvert T

¡P         Marine Piling

¡P         Construct ion of socket-H pile

¡P         Construction works for Culvert U

¡P         Construction of 1500f drainage pipe

¡P         Construction of Pile cap & column (Land)

¡P         Dismantling of marine platform

¡P         Demolition of parapet at IEC Link

¡P          Noise level shall be controlled by reducing the pilling operation rate.

¡P          Noise barrier shall be implemented.

¡P          Dust control during dust generating works

¡P          Provide protection works and adequate drainage system to ensure no direct discharge into public drainage system or the sea.

HK2009/01

¡P         Installation of pre-bored H-pile in CWB stage 2 (from Ch120 to Ch190) when the modification of piling rig to suit the low headroom area was completed.

¡P         Remedial works for SCL Diaphragm Wall

¡P         Installation of dewatering system and equipment at SCL

¡P          Backfilling works of the Area 3 to the required level

¡P         Noise level shall be controlled by reducing no. of plants working in parallel.

¡P         Well maintained enclosures for grouting and bentonite mixing plants.

¡P         Provide protection works and adequate drainage system to ensure no direct discharge into public drainage system or the sea.

¡P         Dust control during dust generating works

 

HK/2009/02

¡P         Deep excavation and strut installation works below -20mPD to -23mPD on the eastern and western portion

¡P         Diaphragm wall construction for Panel P116, C107, P114, BHP5, BHP3 and BHP7

¡P          Well maintain the enclosures for grouting and bentonite mixing plants.

¡P          Dust control during dust generating works

¡P          Provide protection works to ensure no runoff out of site area or direct discharge into public drainage system.

HK/2010/06

¡P         Construction of Pre-cast Unit in China

¡P         Air pollution control during transportation

 

10.0.3.    The construction works of Contract no. 04/HY/2006 ¡V Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A was completed, and the FEP was surrendered by the Contractor on 11 February 2011.